Placing a container in the public right-of-way in Appleton requires a permit from City of Appleton Department of Public Works — Engineering Division. Your own driveway does not. The fee is $40, verified on the city's own permit page, and it takes up to 5 business days.

Street or right-of-way
Permit required
Private driveway
No permit required
Cost
$40
Lead time
5 business days

What permit you need and who issues it

Permit to Occupy the Public Right-of-Way ("Occupancy Permit")

Issuing department: City of Appleton Department of Public Works — Engineering Division

What it costs and how to apply

$40 — Non-refundable. Verified on the city’s own permit page on 2026-08-17.

Allow up to five full business days. Applications are processed in the order received, and work must not start until the permit is issued.

Application, supporting documents and payment confirmation are submitted by email to [email protected].

If you can use your driveway instead

Do that. It removes the permit, the lead time and the expiry date from your project in one move. Ask the hauler to lay boards under the container rails and the truck wheels, because a loaded roll-off concentrates several tons onto a small contact area and driveway damage is normally excluded from their liability.